Hereward Hall, March

Delivering a Constrained Urban Edge Development with Integrated Design & Build Control

Snowdon Homes is delivering a high-quality residential development at Hereward Hall, March, in partnership with Flagship Housing.

Comprising 19 new homes, the scheme demonstrates Snowdon Homes’ ability to deliver urban edge and infill-style developments, where adjacency, drainage, access and buildability must be carefully coordinated under a fully integrated Design & Build approach.

housing partner

Building on a successful partnership with Flagship Housing Group

delivery

19 homes comprising 14 Affordable Rent and 5 Shared Ownership properties.

procurement partnership

Delivered under a fixed-price JCT Design & Build 2024 throughout a 78-79 week delivery period

Project Overview

The Hereward Hall scheme delivers a carefully designed medium-density development, comprising:

  • Primarily 2-bedroom family homes, supported by 3- and 4-bedroom units
  • A density of approximately 31 dwellings per hectare, optimising the site while respecting its context
  • A layout that integrates with surrounding uses, including adjacent buildings, open space and existing access infrastructure

The development is positioned adjacent to the existing Hereward Hall complex, car park and playing fields, requiring careful design integration and site coordination.

Key Challenges Solved

This scheme is defined by site constraints and ground/infrastructure conditions, requiring a buildability-led approach:

1

High groundwater table, impacting substructure and drainage design

2

Requirement for a package pump station, including deep below-ground infrastructure

3

Piling and structural solutions, delivered using a Speedeck system

4

Tree Preservation Orders (TPOs) influencing layout and external works

5

Use of a private council road, requiring license agreements and coordination

6

Tight spatial coordination with existing buildings, access and parking

Our Process

Section Agreements & Infrastructure Delivery

The project includes a focused but important set of statutory and infrastructure considerations:

  • Section 106 Agreement – Affordable housing and planning obligations. 
  • Council Licence Agreement – Required due to use of the existing council-owned/private access road. 
  • Private Road Access Arrangements – Ongoing management of third-party access rights. 
  • Pump Station Infrastructure – Coordination of specialist drainage infrastructure. 
  • Tree Preservation Order (TPO) Constraints affecting layout and delivery. 

Snowdon Homes manages these elements through:

  • Early-stage coordination with stakeholders
  • Integration of design and approvals into programme planning
  • Careful sequencing of below-ground and infrastructure works

This ensures programme certainty and long-term reliability for the Client.

Design & Build – Unlocking a Constrained Site

Snowdon Homes is delivering the scheme under a fully integrated Design & Build model, taking ownership of:

  • Design coordination across all disciplines
  • Drainage and ground engineering solutions
  • Infrastructure and access strategy
  • Construction methodology and sequencing

Working with Welland Design and Rossi Long, the project benefits from a cohesive technical team, ensuring alignment between design intent and practical delivery.

Programme Control & Delivery

Start on Site: September 2025

Duration: Approximately 78–79 weeks

Completion: March 2027

Programme Variance: Controlled and slightly improved programme delivery

Commercial Performance and Control

  • Removal of a required substation, delivering cost and programme benefits

Snowdon Homes has maintained:

  • Tight commercial control
  • Minimal variation exposure
  • Strong cost certainty for the Client

Digital Delivery & Transparent Governance (Procore-led IMS)

To manage a constrained and technically coordinated site, Snowdon Homes utilises its Procore-led Integrated Management System (IMS).

This provides:

  • A single source of truth across all project data
  • Time-stamped, auditable records of decisions and approvals
  • Real-time visibility for Flagship and the Employer’s Agent
  • Seamless communication across all project stakeholders

Integrated systems include:

  • Procore – governance, document control and reporting
  • Breadcrumb – health & safety compliance
  • Asta Powerproject – programme sequencing
  • Sage – financial management

Quality, Compliance and Accreditations

Snowdon Homes operates under a fully accredited management framework:

  • ISO 9001 – Quality Management
  • ISO 14001 – Environmental Management
  • ISO 45001 – Health & Safety Management

Supported by:

  • Digital inspections and quality assurance processes
  • Real-time compliance tracking
  • Structured reporting aligned to Employer’s Agent requirements

Additionally:

  • Living Wage Foundation accredited
  • Fair Payment Code compliant

Sustainability & Building Performance

The scheme incorporates a low-carbon, energy-efficient design:

  • Target EPC rating of B
  • Air Source Heat Pumps for heating and hot water
  • Electric vehicle charging provision
  • Waste Water Heat Recovery

This ensures efficient long-term performance and reduced running costs for residents.

Why Hereward Hall Demonstrates Snowdon Homes’ Capability

Deliver urban edge and constrained site developments

Manage groundwater, piling and drainage complexity

Coordinate infrastructure within tight spatial and access constraints

Maintain programme and cost certainty on technically demanding sites

Provide full transparency through digital project governance systems

July 2026

July 2026